Construction Updates

Printed Mon Sep 23 2019 14:15:35 GMT+0000 (Greenwich Mean Time)

Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with the louvers, painting, brickwork, plastering, skim coating, ceilings, plumbing, wiring and tiling and started with the form work for the swimming pool.

NaN/6

Bali Water World A
Bali, Indonesia

   1. Structural Works
          - Building A : 97%
          - Lower Ground Floor & Pool  : 29%
     2. Architectural Works
          - Building A  : 31%
     3. Mechanical, Electrical and Plumbing works (MEP)
          - Building A  : 31%

NaN/5

Bali Water World B
Bali, Indonesia

   1. Structural Works
          a. Building B : 97%
          b. Lower Ground Floor & Pool  : 29%
      2. Architectural Works
          a. Building B  : 33%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 33

NaN/4

Bali Water World C
Bali, Indonesia

     1. Structural Works
         a. Building C : 97%
         b. Lower Ground Floor & Pool : 29%
      2. Architectural Works
          a. Building C : 23%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 19%

NaN/4

Bali Water World D
Bali, Indonesia

1. Structural Works
         a. Building D : 100%
         b. Pool : 96%
     2. Architectural Works
          a. Building D : 87%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 71% 

NaN/5

Bali Water World E
Bali, Indonesia

 1. Structural Works
         a. Building E : 100%
         b. Pool : 96%
     2. Architectural Works 
         a. Building E : 67%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 70%

NaN/3

Chumphon Building 3
Chumphon, Thailand

Completed: 64 %
  • Working on roof structure (100%).
  • Tiling work in bathroom.
  • Tiling corridor.
  • Wall behind building (done).
  • Aluminum fence install (done).
  • Ceiling work.
  • Pouring the concrete for the pool (done).
  • Outdoor painting.
  • Indoor painting.
  • Start swimming pool system.
NaN/11

Chumphon Coral Beach Villas Plot 29
Chumphon, Thailand

•   Painting work (done)
•   Gardening around the villa
•   Start system work for swimming pool (done)
•   Assemble furniture
•   Sand wash around the pool (done)
NaN/7

Chumphon Coral Beach Villas Plot 31
Chumphon, Thailand

  • Start system work for swimming pool (done)
  • Sand wash around the pool (done)
  • Gardening around the villa
  • Assemble furniture
  • Start doing wall paper
  • Install aluminum fence
NaN/8

Samui Resort building A
Koh Samui, Thailand

Completed: 100
  • Front wall plastering elevator 1st and 2nd  floor.
  • Tile laying fire exit stair 3rd  and 4th floor.
  • Tiling main stairs 2nd and 3rd  floor.
  • Tiling the corridor floor.
  • Keep external paint work
  • Setting up guard rail 4th floor.
  • Setting ceiling 4th floor.
  • Install the power cord in to the Main Distribution Board.
  • Install lamp wall.
  • Install electrical cabinets in the room 3rd  floor.
  • Install sanitary ware 1st and  3rd floor.
  • Install aisles lamp 3rd floor.
  • Install sandstone on the wall.
  • Install doors flame and door 4th floor.
NaN/9

Samui Resort building B
Koh Samui, Thailand

Completed: 100
  • Plastering outside the building was completed.
  • Setting up elevator 95%.
  • Install electrical switches and electrical plugs 3rd floor.
  • Tile laying fire exit stair 3rd  and 4th floor.
  • Tile laying 4th floor.
  • Install sanitary ware 1st to 4th floor.
  • Install ventilation fans 2nd floor.
  • Setting up guard rail 4th  floor.
  • Setting ceiling 4th floor 95%.
  • Install the power cord in to the Main Distribution Board.
  • Install doors 1st floor.
  • Install floor tiles  4th  floor.
  • Install sandstone on the wall.
  • Setting up guard rail 4th floor.
NaN/10

Samui Resort building C
Koh Samui, Thailand

Completed: 100
  • Install air conditioner  2nd floor.
  • Install rainwater pipes.
  • Install aisles lamp 3rd floor.
  • Install water meter3rd floor.
  • Plastering outside the building.
  • Tiling the corridors   2nd and  3rd floor.
  • Tile laying main stairs 2nd and 3rd  floor.
  • Install the ceiling structure 4th floor.
  • Install lamp wall.
  • Fire testing system.
  • Install the main electrical cable set, 2nd floor
  • Install up guard rail 4th floor.
  • Setting up elevator 95%.
  • Tile laying fire exit stair 3rd and 4th floor.
  • Install granite on the wash basin 4th floor.
NaN/9

Samui Resort building D
Koh Samui, Thailand

Completed: 100
  • Install the ceiling structure 4th floor.
  • Install ceiling 4th floor.
  • Install SHERA wall.
  • Install air conditioner 2nd floor.
  • Install rainwater pipes.
  • Potted plastering 3rd and 4th floor.
  • Tile laying fire exit stair 3rd and 4th floor.
  • Tiling the corridors  2nd and 3rd floor.
  • Install floor tiles 2nd floor was completed.
  • Plastering elevator wall.
  • Setting up guard rail 4th floor was completed.
  • Install electrical cabinets in the room 3rd floor.
  • Painting ceiling 3rd floor was completed.
  • Install air conditioned 4th floor
  • Install main water meter 1st and 2nd floor.
  • Setting up elevator 95%

 

NaN/10

Samui Water World building A
Koh Samui, Thailand

  • Pouring the base concrete was completed.
  • Setting up the scaffold for 2nd floor.
  • Pouring concrete 1st floor was completed.
  • Setting groundwater storage tank frame was completed.
  • Install the plumbing system 1st floor.
  • Setting main pipe system 1st   floor.
  • Pouring concrete elevator wall 1st floor was completed.
  • Pouring concrete pole 1st floor was completed.
NaN/6

Samui Water World building B
Koh Samui, Thailand

  • Steel pole tile 1st floor.
  • Tied steel frame elevator wall.
  • Laying steel base.
  • Tie steel frame base.
  • Tied steel pole 1st floor.
  • Setting main pipe system 1st   floor.
  • Install the plumbing system 1st floor.
  • Tied beam frame.
  • Pouring concrete beam.
  • Setting ground water system.
  • Pouring concrete 1st floor.
NaN/4

Samui Water World building C
Koh Samui, Thailand

  • Tied steel frame elevator wall was completed.
  • Pouring concrete poles was completed.
  • Pouring concrete the groundwater storage tank was completed.
  • Install the plumbing system 1st floor.
  • Pouring concreate post tensioned 1st floor was completed.
  • Setting steel floor frame 1st floor
  • Steel pole tile 1st floor.
  • Pouring concrete 1st floor.
  • Pouring concrete pole 1st floor.
  • Setting up floor frame 2nd floor.
NaN/4

Samui Water World building D
Koh Samui, Thailand

  • Cut the foundation pile.
  • Tie steel frame base.
  • Steel pole tie 1st floor.
  • Pouring concrete base was completed.
  • Pouring concrete pole 1st floor was completed.
  • Setting up the scaffold for 2nd floor.
  • Tied steel beam pool bar.
  • Setting main water pipe system 1st floor.
  • Tied steel frame pool bar wall.
  • Install the plumbing system 1st floor.
  • Tile steel pole frame 1st floor.
NaN/4

Boutique
Pattaya, Thailand

Completed: 65 %
  • Plastering work on 6th floor 90% completed.
  • Plastering work on 7th floor 20% completed.
  • Exterior plastering work 85% completed.
  • Bricklaying on 7th floor 100% completed.
  • Tilling bathroom wall on 3rd-5th floor 95% completed.
  • Tilling bathroom wall on 6th floor 70% completed.
  • Tilling on 1st floor 60% completed.
  • Tilling  on 2nd-4th floor 80% completed.
  • Tilling on 5th floor 60% completed.
  • Ceiling work on 1st-4th floor 75% completed.
  • Ceiling work on 5th floor 60% completed.
  • Electric system work on 2nd-4th floor 92% completed.
  • Water drains work on 2nd-7th floor 85% completed.
NaN/11

Castle 1
Pattaya, Thailand

Completed: 100
  • Construction work 100% completed.
  • Architecture work 100% completed.
  • Sanitation systems work 100% completed.
  • Electric work 100% completed.
NaN/12

Castle 2
Pattaya, Thailand

Completed: 99 %
  • Bricklaying work on the underground floor 99% completed.
  • Plastering work on 1st-8th floor 99% completed.
  • Plastering wall work on rooftop floor 99% completed.
  • Plastering underground wall 99% completed.
  • Wash basin counter work 85% completed.
  • Tilling work on 1st-8th floor 99% completed.
  • Tilling work on rooftop floor 99% completed.
  • Install skirting boards 95% completed.
  • Install wood door 30% completed.
  • Outdoor painting work 40% completed.
  • Interior wall painting work 80% completed.
  • Exterior painting work 50% completed.
  • Ceiling work 72% completed.
  • Installing UPCV window on 2nd-7th floor 85% completed.
  • Elevator work 80% completed.
  • Electric system work 1st-8th floor 99% completed.
  • Water system work 97% completed.
NaN/11

Castle Hotel
Pattaya, Thailand

  • Electric system on 2nd floor.
  • Painting ceiling work on 2nd floor.
  • Wall work on 1st floor.
  • Roof top work.
  • Installing Air condition on 2nd floor.
NaN/5

Club 3
Pattaya, Thailand

Completed: 100
  • Almost completed (Just wait for cleaning).
  • Open on August 2019
NaN/9

Club 4
Pattaya, Thailand

Completed: 92 %
  • Ceiling work on 1st floor 80% completed.
  • Ceiling work on 2nd-7th floor 100% completed.
  • Swimming pool electrical system work 100% completed.
  • Exterior painting work 98% completed.
  • Painting in the room on 2nd-7th 99% completed.
  • Water drains work on 2nd-7th floor 100% completed.
NaN/11

Club 5
Pattaya, Thailand

Completed: 5 %
  • Adjust the soil 70% completed.
  • Pouring foundation concrete 55% completed.
  • Foundation work 100%
NaN/6

Palace Hotel
Pattaya, Thailand

Completed: 14 %
  • Sheeting support pole on 1st floor 100% completed.
  • Setting elevator plan underground floor 100% completed.
NaN/6

Bangtao Water World B
Phuket, Thailand

  • Installing environmental quality measurement equipments.
  • The piling work of building D done around 26%.
  • Digging foundation work for building B.
  • Building the retaining wall block.
  • Making a foundation work of retaining wall.
  • Steel building wire work for the base of retaining wall.
NaN/6