Construction Updates

Printed Tue Jan 21 2020 12:50:35 GMT+0000 (Greenwich Mean Time)

Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with floor and wall tiles, waterproofing, wall plastering, ceiling work, installing handrails on the balconies, beam installation for elevators, brick wall installation, rebar and I-beam installation for decking.

NaN/10

Bali Water World A
Bali, Indonesia

     1. Structural Works
          - Building A : 98%
          - Lower Ground Floor & Pool  : 43%
     2. Architectural Works
          - Building A  : 36%
     3. Mechanical, Electrical and Plumbing works (MEP)
          - Building A  : 34%

NaN/6

Bali Water World B
Bali, Indonesia

1. Structural Works
          a. Building B : 98%
          b. Lower Ground Floor & Pool  : 43%
      2. Architectural Works
          a. Building B  : 40%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 45%

NaN/5

Bali Water World C
Bali, Indonesia

1. Structural Works
         a. Building C : 98%
         b. Lower Ground Floor & Pool : 43%
      2. Architectural Works
          a. Building C : 41%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 31%

NaN/6

Bali Water World D
Bali, Indonesia

1. Structural Works
         a. Building D : 100%
         b. Pool : 98%
     2. Architectural Works
          a. Building D : 94%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 75% 

NaN/5

Bali Water World E
Bali, Indonesia

   1. Structural Works
         a. Building E : 100%
         b. Pool : 98%
     2. Architectural Works 
         a. Building E : 76%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 72%

NaN/5